Rock Island District Header Image

ROCK ISLAND DISTRICT

Home



Posted 5/2/2017

Bookmark and Share Email Print


Contact
FERC Hydropower Coordinator
309-794-5599
cemvr-pm-web@usace.army.mil

Location
Des Moines River, Lake Red Rock, Pella, Marion Co., IA

Description
Upon completion, the project will generate 36.39 MW of electricity, which will be transmitted to the power grid in Pella IA by a combination of underground and overhead transmission lines. The construction of this facility will require the penetration of the existing Corps dam impounding Red Rock Lake. Additionally a powerhouse will be constructed at the downstream toe of the dam.

Status
This project is authorized and licensed by the Federal Energy Regulatory Commission, (FERC Project No. 12576) under the Federal Power Act. As part of the license agreement, the hydropower developer, Missouri River Energy Services, (MRES) was required to obtain USACE approval for the project under Section 408. This approval included technical reviews of the project design, review of the operating plan, review of the water quality protection monitoring plan, review of fishing access designs, review of the avian protection plan, review of the Indiana bat protection plan, cultural resources protection consultation, review of the hazmat spill emergency action plan, review of the system safety management plan, review of the emergency operations plan, and general oversight of construction. The USACE review team included technical experts from the Rock Island District, Mississippi Valley Division, USACE Headquarters and USACE Risk Management Center. The USACE review occurred simultaneously with an Independent External Peer Review conducted by a team of experts from across the country. FERC technical experts also reviewed the proposed hydroelectric project.

The developer's Section 408 submittal was received on August 27, 2013 and the Rock Island District completed its review in October 2013. HQUSACE completed its review and the Director of Civil Works approved the Section 408 Modification permit on March 7, 2014. The contractor, Ames Construction from Burnsville MN began construction on August 4, 2014. Ms. Jo-Ellyn Darcy participated in the groundbreaking ceremony that was conducted on August 13, 2014. Construction is ongoing and is scheduled to be substantially completed in February, 2019.

Authority
OM - Operations and Maintenance

Summarized Project Costs

Estimated Federal Cost  N/A 
Estimated Non-Federal Cost  $400,000,000 
Estimated Total Project Cost  $400,000,000 
Allocations Prior to Current FY 2017 Cost  $2,357,768 
Current FY 2017 Allocation (received to date)  $500,000 
Current FY 2017 Total Capability  $500,000 


Major Work Item Current Year
FY 2017:
MVR responsibilities include review of various submittals from MRES in support of the ongoing construction. MVR is providing administrative and technical overview, quality assurance and construction observation.