Rock Island District Header Image

ROCK ISLAND DISTRICT

Home



Posted 5/3/2017

Bookmark and Share Email Print


Contact
Program Manager
(309)794-5690
cemvr-pm-web@usace.army.mil

Location
United States

Description
Section 205, small flood risk management program provides support for local flood risk management by the construction or improvement of structural or non-structural flood risk management measures. Typical structural flood risk management measures may include levees, floodwalls, pumping stations, and channel modifications. Typical non-structural measures may include flood proofing, relocation of structures, elevation of structures, and flood warning and preparedness systems.

Section 205 projects have two phases: Feasibility (study) Phase and Design and Implementation Phase. The first $100,000 of the Feasibility Phase are financed at 100% Federal cost. All feasibility costs above $100,000 are cost-shared 50% Federal and 50%non-Federal. If the project advances to the Design and Implementation Phase all costs are cost-shared 65%Federal and 35% non-Federal. The non-Federal partner may utilize work in-kind and land credits to meet a portion of their cost share responsibilities but must provide at least 5% of the total project costs as cash. Once project is constructed the non-Federal partner is responsible for 100% of the operation and maintenance.

Status
Section 205 of the Flood Control Act of 1948, as amended, provides a continuing authority for the Corps of Engineers to develop and construct small flood control projects without the need of specific congressional authorization. A project is recommended for construction only after a feasibility study clearly shows the engineering feasibility, economic justification (benefits exceed costs), and environmental acceptability of the improvement. Each project is cost shared with the federal cost share not to exceed $10 million. This federal cost includes all project-related costs for feasibility studies, planning, design, and construction.

Authority
CA - Continuing Authorities - Section 205

Summarized Project Costs

Estimated Federal Cost  N/A 
Estimated Non-Federal Cost  N/A 
Estimated Total Project Cost  N/A 
Allocations Prior to Current FY 2017 Cost  N/A 
Current FY 2017 Allocation (received to date)  N/A 
Current FY 2017 Total Capability  N/A 


Major Work Item Current Year
FY 2017:
Advance existing projects that have been appropriated funding. Coordinate with communities to identify potential new projects for consideration.