Description
This project would develop an unsteady HEC-RAS model for the Spoon River within Fulton County (including acquisition of channel cross sections to support model development).Currently, there is no historic information that describes the hydraulic basis for the design of the local flood risk management systems along the lower Spoon River nor is there a functioning hydraulic model that could provide baseline hydraulic information for the Spoon River. Such baseline information is necessary to properly assess these systems as part of the USACE Levee Safety Program, the PL84-99 rehabilitation program, and to support emergency management activities by providing a tool to translate local flood forecasts to project specific impacts.

Status
This is a potential new start. Awaiting funding

Authority
FM - Floodplain Management Services

Summarized Project Costs

Estimated Federal Cost  N/A 
Estimated Non-Federal Cost  N/A 
Estimated Total Project Cost  N/A 
Allocations Prior to Current FY 2017 Cost  $0
Current FY 2017 Allocation (received to date)  $0 
Current FY 2017 Total Capability  $10,000 


Major Work Item Current Year
FY 2017:
Begin to develop an unsteady HEC-RAS model for the Spoon River within Fulton County (including acquisition of channel cross sections to support model development).