ROCK ISLAND DISTRICT         NEWSROOM         WHO WE ARE         SERVICES         PROJECTS         USACE HQ
   Rock Island District > Cedar Rapids Flood Risk Management > Frequently Asked Questions


  Home

  Study Area

  Study Background

  Study Status

  Project Fact Sheet

  Peer Review Plan

  Frequently Asked Questions

  News Releases

  Events (Current & Past)

  Points of Contact

  Related Documents & Links

 

Cedar River, Cedar Rapids, Iowa
Frequently Asked Questions

 

 

 

Aerial Photo of Downtown Cedar Rapids Flooding - June 2008

1. How big was the June 2008 event?

 

The June 2008 event is the flood of record. The peak water surface elevation was 732.50 feet North American Vertical Datum (NAVD) from a discharge of about 140,000 cubic feet per second. Based upon the discharge frequency analysis conducted in the Study, this flood was in excess of the 500-year (.002 exceedance probability) event. The previous flood of record within the 107 years of U.S. Geological Survey gage record was 721.0 feet NAVD from a discharge of 73,000 cubic feet per second. This is approximately 12 feet lower than the June 2008 flood event.

2. What is the current damage estimate for the June 2008 Flood?

 

The City’s current damage estimate is $2.4 billion not including economic damages, which the City has estimated to be another $3.3 billion. Ten square miles of land area were flooded by this flood and about 7,200 properties were either damaged or destroyed.

3. Why aren’t levees and floodwalls justified on both sides of the river?

 

In order for the Corps to make a recommendation for Federal interest the damages prevented by the project need to exceed the project costs. Study Alternative 1C affords protection to properties on both sides of the Cedar River; however, its BCR is less than 1.0. In order for the Corps to recommend an FRM project, the BCR must be greater than 1.0.

4. Will water surface elevations change at Eighth Avenue in Cedar Rapids due to the construction of the FRM project?

Hydraulic modeling for the Corps Recommended Plan (Alternative 4 - levees only on the east side of the river) and the City Preferred Plan Alternative 1 (levees on both sides of the river) shows an increase of water surface elevations of approximately 0.3 feet for the 1% annual chance exceedance, or 100-year, event (94,100 cubic feet per second) at the 8th Avenue bridge. The impacts of the 0.2% annual chance exceedance, or 500-year, event (122,000 cubic feet per second) near the 8th Avenue Bridge are approximately 0.7 feet for Alternative 4 and 3 feet for Alternative 1.

The results are presented in Table A-31 and Figures A-6 and A-7 of Appendix A – Hydraulics and Hydrology report.

5. Will water surface elevations change upstream of Cedar Rapids due to the construction of the FRM project?

Hydraulic modeling for the Corps Recommended Plan (Alternative 4 - levees only on the east side of the river) and the City Preferred Plan Alternative 1 (levees on both sides of the river) shows an increase of water surface elevations of approximately 0.1 feet and 0.3 feet, respectively, at Edgewood Road for the 1% annual chance exceedance, or 100-year, event (94,100 cubic feet per second). The State of Iowa regulates the floodplain for the 1% annual chance exceedance, results of the model show that the impacts upstream are within the regulations for the 1% annual chance event for both Alternatives 1 and 4.

The hydraulic model for the Cedar Rapids Feasibility Study was extended upstream to the Linn County line to estimate the potential upstream impacts of Alternatives 1 and 4 for larger magnitude flooding events. The impacts of the 0.2% annual chance exceedance, or 500-year, event (122,000 cubic feet per second) for Alternative 4 are approximately 0.3 feet at Edgewood Road and are negligible at Palo.

The impacts of the 0.2% annual chance exceedance event for Alternative 1 are 2.5 feet at Edgewood Road tapering down to 0.5 feet at Palo. The model results show an increase of approximately 1 foot in Palo for a 140,000 cubic feet per second flow (2008 event) for Alternative 1. The model results at Palo are estimates because Alternative 1 was determined to not be the Corps Recommended Plan and hydraulic modeling efforts to determine the impacts of Alternative 1 were scaled back. As a result, the best available information was used to extend the model from Edgewood Road to the Linn County line. Channel data was not available and the model assumes channel geometry. For large floods this level of detail is acceptable for planning efforts because the majority of the flow is conveyed overbank.

The results are presented in Table A-31 and Figures A-6 and A-7 of Appendix A – Hydraulics and Hydrology report.

6. Will water surface elevations change downstream of Cedar Rapids due to the construction of the FRM project?

The reduction of storage from the flood plain by the construction of the Alternative 4 levees is small (0.3%) in comparison to the total volume of water passing Cedar Rapids during a large, infrequent flood. Alternatives 1 and 4 were modeled for the range of flows from 94,100 cfs to 143,300 cfs indicating no additional impacts downstream of the project. The velocities downstream of the project are estimated to be unaffected by Alternatives 1 or 4.

7. How will the construction of Alternative 4C impact historical buildings and other cultural resources?

 

Archeological and architectural resources will be affected by Alternative 4C however, the extent of the impact will not be fully known until a more detailed archeological, architectural and cultural survey is completed. All potential impacts will be avoided to the greatest extent possible.

8. Why was the alignment on the west side along the river’s edge, where the current berms are located, screened out?

 

The West Side River’s Edge Alignment was screened out in Planning Process Iteration Two (starting on page 157 of the Report) based on initial economic analysis BCRs, and Proposed Voluntary Property Acquisition FEMA Locations (page 160 of the Report).

9. Will the construction of a levee on the east side change the flood insurance maps?

 

Changes in the Flood Insurance Rate Maps (FIRM) may result from this study. If a levee(s) were constructed that provided protection against the base (100-year) flood, the FIRM would need to be updated to reflect this line of protection as well as any changes in the base flood profile that result from the project. Additionally, as part of this study effort the flood flow frequency estimates and hydraulic model through Cedar Rapids were updated to include recent flood records and the current river geometry. This analysis resulted in improved estimates of the base (100-year) flood profile for existing conditions that the City may use to request a map revision from FEMA regardless of whether a project is constructed.

10. What will be the result of the Feasibility Study?

 

The result will be a feasibility report which evaluates flood risk management alternatives and makes recommendations regarding implementation of a federal project. In order for the Corps to recommend a project it must be environmentally acceptable, economically feasible, and provide sound engineering alternatives.

11. How does the city’s River Corridor Redevelopment Plan influence the Corps Feasibility Study?

 

Input from the city’s plan was considered in the Corps’ planning process and was analyzed as an alternative. The city has provided a great deal of detailed information that was incorporated into the Feasibility Study Report.

12. What important/significant natural resources may be impacted from levee alignments?

 

No significant impacts to any category of natural resources or important habitats are anticipated.

13. The Corps plan separates the city from its river, what can be done to establish a connection to the river, if the Corps plan is built?

 

The Feasibility Study identified the removable wall favored by the City resulted in higher project costs. As a result the majority of the removable walls were eliminated from the Corps plan. Opportunities to use removable floodwalls, on a limited basis, will be considered during the design phase.

14. Why didn’t the Corps plan make a greater use of non- structural options?

 

Non-structural options were considered extensively as the Corps formulated flood risk management plans for the Cedar River at Cedar Rapids, but none were economically justified. The city with the assistance of other federal agencies is implementing a voluntary buyout program which is a non structural option. Additionally, the Iowa – Cedar River Basin study will consider the application of non-structural measures throughout the basin.

15. How soon will construction of the Corps project begin?

 

There is no simple answer to this question as many things have to happen over which the Corps has no control, in order for construction to begin. Key items affecting the schedule that have not occurred are passage of Congressional authorization and funding. After these two key Congressional actions are passed, the earliest construction could start is approximately 2 years.

 

 


  This site is hosted by the Rock Island District, US Army Corps of Engineers
  Rock Island District is part of the Mississippi Valley Division of the U.S. Army Corps of Engineers, Department of Army

Contact Us | Privacy & Security | Disclaimers | Freedom of Information Act (FOIA) | Site Feedback

For questions about the Rock Island District, email or call: CEMVR-CC@usace.army.mil at 309-794-4200 or FAX: 309-794-5793

U.S. Army Engineer District, Rock Island
Clock Tower Building
Rodman Avenue
Rock Island, Illinois 61299
Mailing and Driving Directions

 Contact Information for USACE in Washington D.C. HQ and Entire Corps of Engineers

 For webmaster related comments, improvements, usability, accessibility of this site - email: WebManager@usace.army.mil