**NOTICE** The Illinois Waterway Lock Closures are now underway. Should changes to the schedule be needed, they will be posted in RED on this website as soon as they are available.
**NOTE: Projects and dates listed below are contractual completion dates and do not necessarily reflect the exact date each lock will reopen. The schedule is subject to change due to river levels, weather conditions, health and safety concerns due to COVID-19, project funding, and unknown circumstances that may be discovered during rehabilitation.
2020
LaGrange Lock and Dam – Opened to navigation Oct. 13. - Intermittent delays may occur.
Peoria Lock and Dam – Opened to navigation Sept. 30. - Future 8-hour closures may be needed. These will be announced via the Navigation Notices website.
Starved Rock Lock and Dam – Opened to navigation Oct. 29.
Marseilles Lock and Dam – Opened to navigation Oct. 29.
Dresden Island Lock and Dam – Opened to navigation Oct. 29.
SPECIAL NOTICE (Updated 10/05/20): Two 12-hour closures are anticipated at the Lockport Lock the week of November 30, 2020 (most likely 11/30 and 12/01). These closures are needed for the Rock Island District to provide repair and maintenance support to the Chicago District facility. Additional 10-12 hour closures are also anticipated for late Dec. 2020/Jan. 2021 but these dates and times have not yet been set. These will be announced via the Navigation Notices website.
2023
Dresden Island Lock and Dam – Upper Miter Gate Installation & Electrical Rehab
- Full closure scheduled Summer 2023, approx. 90-120 days
Marseilles Lock and Dam – Electrical Rehab
- Full closure scheduled Summer 2023, approx. 90-120 days
Starved Rock Lock and Dam – Sector Gear Rehab
- Full closure scheduled Summer 2023, approx. 90-120 days
Brandon Road Lock and Dam – Upper Bulkhead Recess Installation & Upper Miter Gate Installation
- Potential to include work at this site if construction projects were approved and funded as part of the Great Lakes Mississippi River Interbasin Study at Brandon Road (GLMRIS-BR).