  • Intermittent road restrictions continue as hydro project progresses

    The mild weather this week has allowed crews at the Red Rock Dam to continue working day and night to prepare the site for construction of a powerhouse and intake structure that will comprise the Red Rock Hydroelectric Project (RRHP). Short-term road closures, directed by the Marion County Sheriff’s Department, will occur in the overnight hours every three to four days as crews move large rebar cages from the North Tailwater staging area to the construction area on the upstream side of the Dam. In addition, Highway T-15 will be restricted to one lane every three to four days to facilitate staging of the concrete trucks to ensure worker and public safety as the wall element sections are poured.
  • Missouri RiverEnergy Services Announces Plans to Build Hydro Facility

    SIOUX FALLS , S.D. - Missouri River Energy Services (MRES) has announced its intent to proceed with