Location
Des Moines Metropolitan Area
Description
This project is a proposal to raise portions of Des Moines I, II and III levee systems, and to raise and relocate portions of the Southeast Des Moines levee system, which is part of the Lake Red Rock Remedial Works. The proposed levee raises range from approximately 6 inches to 4.0 feet. The purpose of the proposed levee raise is to comply with FEMA’s levee certification requirements.
Background
In May 2017, the city of Des Moines submitted an initial comprehensive plan that described all the proposed levee modifications and associated mitigation actions the City is requesting Section 408 permissions. The Rock Island District reviewed this plan and approved it on July 20, 2018. The Rock Island District also entered into a cultural programmatic agreement with the City and the State Historical Preservation Office to ensure compliance with Section 106 of the National Historic Preservation Act.
Status
Following the approval of this conceptual plan the city began submitting detailed plans for each levee system for final review and approval. The City has identified eight phases (A-H) for submittal of detailed plans. Phase A was approved in 2020. Phases B and C were approved in 2022. Phase E 30% plans were reviewed and approved in 2022. The City is actively advancing design and real estate acquisition processes on the remaining portions of the levee system, nothing is currently under 408 review with USACE. In September of 2022 the City requested through the District's Levee Safety Program that USACE partner with the City to conduct a semi-quantitative risk assessment (SQRA) on the Des Moines I levee. The outcome of this study will influence the design of the remaining phases. The SQRA Cost Share Agreement was executed in July 2023 and is scheduled to be completed within two years.
Additional Information
Authority
33 USC 408 (Section 408) and Lake Red Rock Remedial Works Authorities
Summarized Project Costs
Estimated Federal Cost
|
$976,000
|
Estimated Non-Federal Cost
|
$559,000
|
Estimated Total Project Cost
|
$1,535,000
|
Allocations Prior to FY 2024
|
$460,000
|
FY 2024 Allocation
|
TBD
|
FY 2025 President’s Budget
|
TBD
|
FY 2025 Total Capability
|
$45,000-$70,000
|
Major Work Item Current Year
FY 2024: During FY 2024, the District continued to review and coordinate the city of Des Moines’s Sec 408 request to ensure responses and determinations align with the city’s construction schedule. The city is designing and constructing these modifications at their expense. The District also plans to complete the SQRA on the Des Moines I levee.
Major Work Item Next Fiscal Year
FY 2025: If funded, work will proceed on coordination with the City and their A/E design firms, review and approval of final plans and specifications, review of real estate requirements, and ensure environmental compliance on phases D-H segments and minor construction modifications on phases A-C.