Red Rock Hydroelectric Project

Rock Island District
Published Oct. 1, 2021
Red Rock Hydropower Powerhouse

Red Rock Hydropower Powerhouse

Location

Des Moines River, Lake Red Rock, Pella, Marion County, Iowa

Description

The project will generate 36.39 MW of electricity, which will be transmitted to the power grid in Pella, Iowa, by a combination of underground and overhead transmission lines. The construction of this facility required the penetration of the existing Corps dam impounding Red Rock Lake. Additionally, the powerhouse was constructed at the downstream toe of the dam.

Background

This project is authorized and licensed by the Federal Energy Regulatory Commission, (FERC Project No. 12576) under the Federal Power Act. As part of the license agreement, the hydropower developer, Missouri River Energy Services, (MRES) was required to obtain USACE approval for the project under Section 408. This approval included technical reviews of the project design, review of the operating plan, review of the water quality protection monitoring plan, review of fishing access designs, review of the avian protection plan, review of the Indiana bat protection plan, cultural resources protection consultation, review of the hazmat spill emergency action plan, review of the system safety management plan, review of the emergency operations plan and general oversight of construction. The USACE review team included technical experts from the Rock Island District, Mississippi Valley Division, USACE Headquarters and USACE Risk Management Center. The USACE review occurred simultaneously with an Independent External Peer Review conducted by a team of experts from across the country. FERC technical experts also reviewed the proposed hydroelectric project.

The developer's Section 408 submittal was received on August 27, 2013 and the Rock Island District completed its review in October 2013. HQUSACE completed its review and the Director of Civil Works approved the Section 408 modification permit on March 7, 2014. The contractor, Ames Construction from Burnsville, Minnesota, began construction on August 4, 2014. Ms. Jo-Ellyn Darcy participated in the groundbreaking ceremony that was conducted on August 13, 2014.

Status

The powerhouse and intake structure are complete. A ribbon cutting was held 2 September 2020. Commissioning has been completed.

Additional Information

Authority

OM - Operations and Maintenance

Summarized Project Costs

Estimated Federal Cost

$ N/A

Estimated Non-Federal Cost

$ 400,000,000

Estimated Total Project Cost

$ 400,000,000

Allocations Prior to FY 2022

$ 4,645,350

FY 2021 Allocation

$ 100,000

FY 2022 Allocation

$ 0

FY 2022 President’s Budget

$ 0

FY 2022 Total Capability

$ 0

 

Major Work Item Prior Fiscal Year

FY2021: MVR responsibilities include completing final coordination. No further work is expected in FY22.