Location
Pool 14, Upper Mississippi River Miles 517.0-513.0
Clinton County, Iowa
Description
The Beaver Island Habitat Rehabilitation and Enhancement Project, part of the Upper Mississippi River Restoration program, is located along the right descending bank of the Upper Mississippi River in the southern portion of Clinton County, Iowa. Lock and Dam 13 is located 5 miles upstream of the island system. The project lands, part of the Upper Mississippi River National Wildlife and Fish Refuge, are federally owned. The project area is comprised of 1,678 acres of interconnected backwaters, secondary channels, wetlands, and floodplain habitat.
The goals are to restore and protect aquatic, wetland, and floodplain forest habitats. The objectives identified to meet these goals are (1) increase year-around aquatic habitat diversity and native fish use of spawning, rearing and overwintering habitat; (2) diversify floodplain forest habitat; (3) increase structure and function of side channel habitat.
Project Features:
- Excavate channels in backwater areas
- Construct elevated berms using excavated channel material
- Plant hard mast producing trees on the elevated berms
- Use timber stand improvement techniques
- Place a rock closure structure on the island’s upstream end
- Construct a chevron, place bank protection, and provide mussel substrate at Albany Island
The Recommended Plan would restore backwater habitat by excavating backwater channels to a depth of 8 feet or more below flat pool to provide overwinter and year-around habitat for fish. Excavated material will be used to construct land berms to enhance topographic diversity. The land berms will be planted with native floodplain forest vegetation and trees. Other timber stand improvement actions will also occur such as tree release, girdling and interspersed tree plantings. A rock closure structure will be constructed at the entrance to Upper Cut on Beaver Island’s upstream end to reduce overwintering water velocities and sediment deposition.
Background
Human activity, such as channel manipulation for navigation purposes, over the past two centuries within the UMR basin, floodplain and channel has altered the hydrology, topography and biotic communities present in the Project area. These alterations have reduced the diversity and quality of aquatic habitat, reduced the acreage and diversity of the native floodplain forest, and reduced the acreage and diversity of isolated ephemeral wetlands. While these stressors are likely to continue, as will the decline of the quality of aquatic, wetland and floodplain habitat, this Project provides an opportunity to improve the quality and diversity of critical habitats.
The need for the project is based on the following factors:
- The existing aquatic habitat currently lacks adequate centrarchid overwintering habitat (i.e., depth and flow) important for year-round habitat functioning. Without action, the available overwintering habitat will continue to decrease.
- The existing topography lacks floodplain forest diversity, and a significant amount of the island is inundated during a typical flooding event. Consequently, floodplain forest regeneration, growth and survival are reduced. Without action, floodplain habitat will decrease in quality through succession to silver maple, open canopy and/or reed canary grass, which is an invasive species.
- Albany Slough, the existing secondary channel habitat, has degrading geomorphologic features, structure, and function. Over time, Albany Island is likely to continue eroding, which would have major detrimental effects on existing mussel communities inhabiting the Albany Slough and on the fish species which serve as hosts.
Status
The feasibility report was approved in June 2017. The Stage IB construction contract was awarded January 2019 and was completed in May 2023. In April 2020, timber stand improvements and tree plantings started and are scheduled to be completed by December 2024.
Additional Information
Authority
Water Resource Development Act (WRDA) of 1986 under Section 1103 (33 U.S.C 2201 et seq.; P.L. 99-662, 1986)
CG - Construction General
Summarized Project Costs
Estimated Federal Cost
|
$25,288,000
|
Estimated Non-Federal Cost
|
$0
|
Estimated Total Project Cost
|
$25,288,000
|
Allocations Prior to FY 2024
|
$20,971,994
|
FY 2024 Allocation
|
$0
|
FY 2025 President’s Budget
|
$0
|
FY 2025 Total Capability
|
$0
|
Major Work Item Current Year
FY 2024: The Project moved forward with the closeout of Stage IB construction and timber stand improvements and tree plantings. The monitoring will be applied using active adaptive management principals to help design future HREPs.
Major Work Item Next Fiscal Year
FY 2025: If funded, the project will move forward with the completion of the timber stand improvements and tree plantings, and finalizing the operation and maintenance manual with on hand funding.