Location
Carbon Cliff, Illinois
Description
Carbon Cliff, Illinois, has a history of flooding from the Rock River and an unnamed tributary which runs through a portion of the City. The City would like assistance investigating alternatives, both structural and non-structural, to help reduce damages caused by flooding.
Background
A letter of request has been received from the sponsor. The initial phase of work will be to determine a federal interest.
Status
This is a potential new start. This project is awaiting funding.
Additional Information
Authority
CA - Continuing Authorities - Section 205
Summarized Project Costs
Estimated Federal Cost
|
$364,000
|
Estimated Non-Federal Cost
|
$209,000
|
Estimated Total Project Cost
|
$573,000
|
Allocations Prior to FY 2022
|
$0
|
FY 2021 Allocation
|
$0
|
FY 2022 Allocation
|
TBD
|
FY 2022 President’s Budget
|
TBD
|
FY 2022 Total Capability
|
$100,000
|
Major Work Item Current Year
FY 2022: Potential project new start. Conduct Federal Interest Determination if funded.